The City of Fairview Park is pleased to inform you that the installation of seven water flow meters at various locations in the city began on March 31 (see photos below). The flow meters are being installed by HYDROMAX USA and will determine our sewer system’s capacity on dry days versus days with heavy storms. Measurements are expected to be completed by late summer. Based on the needs identified by the computer model, a master plan will be developed consisting of prioritized improvement projects to be implemented over several years. 

This plan also involves the development of a skeletal model for the neighborhoods on the western border of the city. The company will coordinate the collection of information to create a computer model of the city’s sanitary sewer system. The model will indicate if the sewer system is adequate in size and how badly it is affected by heavy rainstorms.

In the meantime, the City will be exploring potential funding sources for future projects.